The final landed price of used construction machinery exports is only about 60% for the equipment itself; the remaining 40% is hidden in port operations, ocean freight, destination customs clearance, and inland transportation. Take a used excavator shipped to Mombasa, Kenya as an example: the 40-foot container ocean freight from Tianjin Port to Mombasa is about USD 1,800–2,600 in the off-season and may double in peak season; destination customs clearance agency fees, terminal handling charges, and demurrage often fluctuate between USD 800 and 1,500. Getting the logistics account clear is more practical than bargaining down the equipment price.
Domestic Segment: Pace Control for Port Consolidation and Customs Declaration
Equipment is sent from preparation yards in Hebei, Shandong, and Jiangsu to Tianjin Port or Shanghai Port, with road trailer costs calculated by kilometer and vehicle type. For a 20-ton used excavator moved by low-bed trailer from Xuzhou to Shanghai Port, the trailer fee is about RMB 3,500–4,500; mining trucks exceed width and height limits and require oversize transport permits, raising costs by about 30%. Port consolidation time should be scheduled 48 hours before the customs cut-off to allow room for inspection, photographing, and securing.

- Customs declaration documents: contract, invoice, packing list, export customs declaration form, equipment inspection report, certificate of origin (if required).
- Key items for used equipment: pre-shipment inspection certificate (mandatory in some countries), equipment nameplate photos, working hour records.
- Securing requirements: tracks and bucket secured with wire rope, cab covered with rainproof tarpaulin, battery disconnected, fuel tank drained to below one quarter.
Sanqi Machinery has long-term cooperative customs brokers and yards at Tianjin Port and Shanghai Port. Used excavators and used loaders generally complete port consolidation to release in 3–5 working days. If inspection occurs, the main check is whether the equipment model and year of manufacture match the declaration; inspection reports and nameplate photos can save considerable explanation time.
Ocean Freight Segment: Route Selection and Transit Time Reference
African routes mainly use Tianjin, Shanghai, and Qingdao ports. West Africa (Lome, Tema) takes about 35–45 days, while East Africa (Mombasa, Dar es Salaam) takes about 28–35 days. Southeast Asian routes depart from Guangzhou and Shenzhen, with Jakarta and Manila taking about 7–12 days. Middle East routes to Jebel Ali take about 18–25 days. Breakbulk vessels are suitable for oversize equipment such as mining trucks, Ro-Ro vessels are suitable for self-propelled used loaders and bulldozers, and containers are suitable for dismantled hydraulic parts and engine parts.
- Breakbulk: charged by volume or weight, commonly used for mining trucks, requiring reserved deck lashing time.
- Ro-Ro: charged by vehicle dimensions, used bulldozers and loaders can be driven directly onto the ship, saving securing costs.
- Containers: suitable for high-value hydraulic parts and engine parts, with high requirements for moisture and rust protection.
Destination Customs Clearance: Costs and Common Bottlenecks
Destination customs clearance is the stage where buyers most easily exceed budget. Take Lagos, Nigeria as an example: import duties plus VAT on used construction machinery often range from 25% to 40% of cargo value, depending on HS code and year. Customs broker fees, terminal charges, inspection fees, and port demurrage are calculated separately. There are three common bottlenecks: first, missing pre-shipment inspection certificates, as some countries require SONCAP or PVoC; second, equipment year not matching the declaration, resulting in additional tax; third, wooden packaging without IPPC fumigation marks, causing the entire shipment to be stuck at the port.
Before export, Sanqi Machinery provides buyers with a checklist of destination country customs clearance requirements, including which documents are needed, approximate tax ranges, and local agent contact information. Buyers can find their own agent or use our cooperative agent; fees are transparent and there is no binding.
Delivery and Acceptance: Don't Rush to Sign After Arrival
After the equipment arrives at the destination port, first check the appearance for shipping damage, then start and test the machine. For used excavators, focus on the hydraulic pump, distribution valve, and travel motor; for used bulldozers, check the gearbox and final drive; for mining trucks, check engine parts, suspension, and tires. After hydraulic parts and engine parts arrive, verify part numbers, packaging, and rust protection. Before signing the acceptance form, photograph and record any issues to facilitate subsequent claims or replacement parts.
- Pre-start checks: battery voltage, fuel circuit, hydraulic oil level, coolant.
- Test items: run at idle, medium speed, and full load for 10 minutes each, observing black smoke, abnormal noise, and leaks.
- Parts verification: check item by item against the packing list; for key parts such as hydraulic pumps and engine cylinder liners, look for original manufacturer markings.
FAQ
What customs clearance documents are generally required for exporting used excavators to Africa?
Usually a contract, invoice, packing list, bill of lading, pre-shipment inspection certificate, and certificate of origin are required. Some countries also require SONCAP or PVoC; confirm with the destination port agent for specifics.
For mining trucks, which is more cost-effective: breakbulk or Ro-Ro?
Mining trucks are oversize and mostly use breakbulk charged by volume, with lashing fees calculated separately. Ro-Ro is charged by vehicle dimensions and is suitable for models that can drive on board, saving securing costs but with fewer slots.
What proportion of the equipment price does logistics cost generally account for in used construction machinery exports?
About 8%–15% for short-sea routes, about 15%–30% for African routes, and possibly up to 35% for South American routes. It depends on the port, shipping schedule, and whether oversize; off-season and peak-season price differences can reach double.
If destination customs clearance is inspected, how long is it generally delayed?
Routine inspection with complete documents is released in 3–7 working days. If additional tax or document discrepancies are involved, it may drag on for 2–4 weeks, with port demurrage accumulating daily. It is advisable to prepare inspection reports in advance.
What should be noted for packaging when exporting hydraulic parts and engine parts?
Hydraulic pumps and distribution valves should be packed in wooden cases with anti-rust oil; engine cylinder liners and pistons should be individually wrapped in bubble film. Wooden cases must have IPPC fumigation marks, otherwise the destination port may reject them or require re-treatment.
If problems are found during machine testing after arrival, how should after-sales be handled?
First take photos and videos as evidence, and refer to the contract warranty terms. Sanqi Machinery provides warranty for core components for an agreed period; parts can be resupplied, requiring part numbers and fault descriptions.